Tuesday, October 3 – AO MOSENERGO’s General Director, A. Ya. Kopsov, will attend the meeting of the Government of Moscow and will present information relating to the preparation of the Company for the autumn-winter peak-load operations for 2006-2007.
Tuesday, October 3 – AO MOSENERGO’s General Director, A.Ya. Kopsov, will hold the meeting on commissioning of the new 25 MW turbine set at HEPS-1.
Wednesday, October 4 – AO MOSENERGO’s General Director, A. Ya. Kopsov, will hold the follow-up meeting on the gas-vapor power units design and construction at TPP-21, TPP-26 and TPP-27.
Friday, October 6 – AO MOSENERGO’s General Director, A. Ya. Kopsov, will attend the All-Russia meeting of RAO UES of Russia on preparations for the autumn-winter peak-load for 2006-2007.
|