On Wednesday, February 21, a meeting will be held at OAO Mosenergo with representatives of Alstom on construction of the PGU-420 power-generating unit at TETs-26.
On Thursday, February 22, a meeting will be held at OAO Mosenergo on questions of the construction of PGU-450T power-generating units No. 3 and No. 4 at TETs-27.
On Saturday, February 24, a meeting will be held at OAO Mosenergo on issuing process data and a design policy for the PGU-450T power-generating unit at TETs-21.
The turbine bases in the new main building of power-generating unit No. 3 at TETs-27 are currently nearing completion, and installation of the power boilers and preparation of the pile foundation of power-generation unit No. 4 are continuing. Installation of the main building’s steelwork is continuing at TETs-21. Preparation of the construction site at TETs-26 for transfer to the general contractor, Alstom, is currently being completed.
Construction of new power-generating units and technical reequipment of OAO Mosenergo’s power plants are based on the latest steam-gas cycle technology, which guarantees an efficiency factor of 52-59% (at plants with steam-power units, the efficiency factor is no more than 38%). The highly efficient steam-gas units allow gas savings of up to 25%, while reducing harmful atmospheric emissions by one-third. Commissioning of the first PGU-450 steam-gas power-generating unit at TETs-27 will take place in the fourth quarter of 2007.
|